Tentative Paving Schedule – Begins June 16, 2025
Dear Residents,
As part of our previously announced major paving project, we are pleased to share the tentative schedule for milling and paving operations, set to begin on Monday, June 16, 2025.
The work will be carried out in multiple neighborhoods over the course of three weeks. Please note that this schedule is subject to change based on weather conditions or other unforeseen delays.
Tentative Paving Schedule by Date:
Week 1: Whispering Marsh Area
Mon, June 16: Milling begins – Black Rush Circle (partial)
Tue, June 17: Finish milling – Black Rush, Hermit Crab Way, Marsh Rabbit Ct
Paving begins – Part of Black Rush
Wed, June 18: Milling – Tall Grass, Short Grass, Whisper Grass
Paving – Hermit Crab, Marsh Rabbit, Black Rush (finish)
Thu, June 19: Milling – Grass Marsh
Paving – Tall Grass, Short Grass, Whisper Grass
Fri, June 20: Paving – Grass Marsh
Week 2: Deer Walk & Dunes Mill
Mon, June 23: Milling – Deer Walk Way
Tue, June 24: Milling – Dune Mill Way
Paving – Deer Walk Way
Wed, June 25: Paving – Deer Walk Way, Begin Dunes Mill Way
Thu, June 26: Paving – Finish Dunes Mill Way
Fri, June 27: Mill & Pave – Ayers Plantation Way (section)
Week 3: Ayers Plantation & Contingency
Mon, June 30 – Thu, July 3: Mill & Pave – Continue Ayers Plantation Way as needed; contingency days for weather delays or catch-up work. There will also be a small repair on Harpers Ferry Way.
We appreciate your patience and cooperation during this important infrastructure improvement project. Please be cautious when traveling through work zones and follow the direction of traffic control personnel.
If you have any questions or concerns, feel free to contact Robert Engermann at 843.654.1542 or rengermann@sw-community.com.